Project Information
Precinct | 1 |
City | San Antonio, District 3 |
Watershed | Upper San Antonio River |
Creek
| Sixmile Creek |
Project Type | Regional Drainage Improvements |
Consultant:
CDM Smith
Contractor:
Capital Excavation Company
Construction Cost:
$2,713,133.05
Advertise:
November 10, 2011
Construction Start:
February 2012
Construction End:
July 2013