Rosillo Creek RSWF

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5

Scope

This project consists of channel improvements and the construction of multiple bridges and bridge-class culvert crossings between FM 78 and Ackerman Road along West Tributary to Rosillo Creek. Bridges will be built along Old Seguin, Binz-Engleman, and Ackerman roads. Culvert crossings will be built along Starfire, Redding, and Kirby roads. Channel improvements will extend from FM 78 to Ackerman Road along West Tributary to Rosillo Creek. Approximately 160 adjacent properties will be removed from the 1% annual chance (100-year) storm event floodplain due to planned improvements and floodplain remapping. In addition, unflooded access will be provided at six roadway crossings during a 1% annual chance storm event.

Project Status

Binz-Engleman and Kirby Drive are complete.  The Contractor is working on the second half of the bridge on Ackerman Road and is working on new box culverts on Starfire Road.

The contractor is completing the rip rap on the channel.  Final overlay on Redding is scheduled for Tuesday, September 6, 2016.

Project Status is Complete

Project Documents

Previous Meetings

  • February 15, 2017: Rosillo Creek Project Ribbon Cutting
  • October 25, 2012: Kirby City Council Meeting
  • January 24, 2012: Rosillo Creek Community Meeting
  • October 20, 2011: Kirby City Council Meeting
  • February 8, 2011: Rosillo Creek Community Meeting
  • October 11, 2010: Rosillo Creek Community Meeting
  • August 19, 2010: Kirby City Council Meeting
  • November 4, 2009: Kirby City Council Meeting