Project Information
Precinct | 2 |
City | San Antonio, Districts 6 & 7 |
Watershed | Leon Creek |
Creek
| Leon Creek |
Project Type | Low Water Crossing |
Consultant:
Unintech Consulting Engineers, Inc
Contractor:
Capital Excavation Co.
Construction Cost:
$8,127,542.42 (Joint Bids with SAWS and AT&T)
Advertise:
October 2010
Construction Start:
January 2011
Construction End:
October 2012