Project NameIDPrecinctStatus
Barbara Drive DrainageSA 32Complete
Bulverde Road at Mud Creek Trib ASC 273Complete
Cacias Road Low Water CrossingSA 454Complete
Calaveras 8 RehabilitationSA 414Complete
Cimarron Subdivision CB 94Detailed
Elm Forest at Turtle Cross StreetMR 311Complete
Evans RoadSC 23Complete
French Creek Trib NWWC – EnvironmentalLC 233Construction
Grosenbacher Road South of MadronaMR 301Complete
Hausman Drainage Project Phase ILC 93Complete
Hausman Drainage Project Phase IILC 103Complete
Henze Road Low Water CrossingSA 471Complete
High Water Detection System Phase ICW 1AllComplete
High Water Detection System Phase IICW 1AllComplete
High Water Detection System Phase IIICW 1AllComplete
Huebner Creek Enhanced Conveyance NWWC Segment 1LC 172Complete
Huebner Creek Enhanced Conveyance NWWC Segment 2LC 172Complete
Huebner Creek Enhanced Conveyance NWWC Segment 3LC 172Construction
Huebner Creek RSWF at Prue RoadLC 153Complete
Ingram Road LWC #58LC 82Complete
Jones-Maltsberger at Elm CreekSC 283Complete
Jungman Road to Medina RiverMR 3A1Complete
Kirkner Road Low Water CrossingSA 464Complete
Knoll CreekSC 43, 4Complete
Laddie Place RSWF Phase IIISA 122Complete
Live Oak Slough – Benton City Road ImprovementsMR 131Complete
Martinez Dam 6ACB 174Complete
Medio CreekMR 321Complete
Mid-Beitel Creek Channel RestorationSC 54Complete
N. Verde Rd. LWCLC 263Complete
North Talley Road LWCsMR 101Construction
Old Fredericksburg RoadLC 273Complete
Olmos DamSA 333Complete
Pearsall Road BridgeMR 111Detailed
Perrin Beitel Channel ImprovementsSC 94Construction
Prue Road at French CreekLC 63Complete
Real Road Low Water CrossingSA 174Complete
Rock Creek NWWC/OutfallSA 63Complete
Roland Avenue BridgeSC 184Complete
Rosillo Creek RSWFSC 154Complete
Salado Creek Tributary D at Ira LeeSC 414Complete
San Pedro Huisache Phase IISA 224Complete
San Pedro Huisache Phase IIISA 222Complete
Schaefer Road Drainage Phase ICB 194Complete
Shane Road Low Water CrossingSA 41Complete
Shepherd Road at Elm Creek & Black Hill BranchMR 81Complete
Sixmile Creek Drainage Improvements – CCR 3SA 431Detailed
Sixmile Creek Drainage Improvements – CCR 4SA 431Detailed
Sixmile Creek Drainage Improvements – Roosevelt BridgeSA 431Detailed
Sixmile Creek Drainage Improvements – S. Flores BridgeSA 431Complete
South Hausman RoadLC 53Construction
St. Mary’s University DrainageSA 492Complete
Toutant Beauregard LWCsLC 343Detailed
VFW DrainageSA 441Complete
Whisper Creek at Hollyhock RoadLC 193Complete
Woodlawn at 36th StreetSA 552Detailed