South Hausman Road

Scope

The work to be performed under this contract shall consist of providing detailed engineering and geotechnical investigation required for the detailed design and preparation of construction documents for the construction of three low water crossings and associated road improvements on S. Hausman Road from approximately 400 feet north of Braefield to Paloma Creek Street.

Project Status

Stay tuned for information about the Pre-Construction Public Meeting Spring 2018

09/02/2016 Update:  The design for this project is 95% complete.

Project Status is Detailed Design

Project Documents

Previous Meetings

  • March 26, 2015: South Hausman Community Meeting